Nakatuta SHPP
Feasibility Study, Assistance in tender award

Client: Indipendent Power Producer
Year: 2015 - 2017
Location: Ruvuma Region - Tanzania
Service Provided: detailed Feasibility Study, EPC, Tender Document, Assistance in Tender Award.

Project

A first revision of a previous study has been carried out by ENCO in 2015 in order to ascertain the main conditions for the viability of the project.The new full feasibility study brings substantial improvement in order to cope with the actual regulatory framework for SHPPs and to reduce the capital cost.

Run-of-river HPP with a 60m long diversion dam and a 1,000m long headrace canal.

Gross head: 41,18 m;

Maximum flow rate: 30.24 to 45 m3/sec

Penstock diameter 3 x 2000 mm; length 86 m

Turbine type: 3 to 4 Francis turbines

Installed capacity: 9,99 MW to 14.6 MW

Energy output: 84 to 118 GWh

 